2012-094 Certificate of Substantial Completion - Diamond ValleyTHE CORPORATION OF THE TOWNSHIP OF ORO- MEDONTE
BY -LAW NO. 2012 -094
Being a By -Law to Authorize the Issuance of the Certificate of
Substantial Completion and Acceptance (Municipal Underground Services)
for Diamond Valley Estates, Plan 51 M -957
WHEREAS Section 51, Subsection (26) of the Planning Act, R.S.O. 1990, Chapter
P. 13, as amended, provides that municipalities may enter into agreements imposed as
a condition to the approval of a plan of subdivision and such agreements may be
registered against the land to which the subdivision plan applies;
AND WHEREAS Council for the Corporation of the Township of Oro - Medonte entered
into a Subdivision Agreement with 2008628 Ontario Ltd. (Diamond Valley Estates
Subdivision) in March 2010 for one hundred and twenty eight (128) residential lots on
Diamond Valley Drive, Emerald Terrace, Topaz Court, Opal Court, Ruby Ridge, and
Sapphire Way.
AND WHEREAS the requirements of this Subdivision Agreement with respect to the
underground works have now been met;
NOW THEREFORE the Corporation of the Township of Oro - Medonte hereby enacts as
follows:
1. That the Certificate of Substantial Completion and Acceptance (Municipal
Underground Services) for Diamond Valley Estates (2008628 Ontario Ltd.), Plan
51 M -957 may now be issued by the Township Engineers (AECOM) in
compliance with the Subdivision Agreement between the Corporation of the
Township of Oro - Medonte and 2008628 Ontario Ltd..
2. That the attached Schedule "A ", Certificate of Substantial Completion and
Acceptance (Municipal Underground Services) shall form part of this By -Law.
3. That this By -law shall come into force and take effect on the final date of passing
thereof.
BY -LAW READ A FIRST, SECOND AND THIRD TIME, AND PASSED THIS 9T"
DAY OF MAY, 2012.
THE CORPORATION OF THE TOWNSHIP OF ORO- MEDONTE
Mayor, H.S: H
7
CERTIFICATE OF
MUNICIPALITY
PROJECT
DEVELOPER
FILE NO.
Description of the Works:
SCHEDULE "A"
AECOM
10.Checkley Street
Barrie, ON, Canada L4NIW1
Mmaecom.com
TOWNSHIP ENGINEERS
SUBSTANTIAL COMPLETION AND ACCEPTANCE
(MUNICIPALUNDERGROUND SERVICES)
Township of Oro- Medonte
Diamond Valley Estates Phase 1
Plan 51M -957
2008628 Ontario Ltd.
12- 89235 -50 (60118278) r43T. 930191
705721 @222 lei
705 734 0764 Tax
• Pumphouse Works in the Diamond Valley Estates Phase 1 Subdivision, Block 131;
• Watermain Works in the Diamond Valley Estates Phase 7 Subdivision from the intersection of
Huron Woods Drive south along 61' dine (115 metres), then east along Diamond Valley Drive to the
intersection of Topaz Court (696 metres);
• Storm Water Management Pond Works in the Diamond Valley Estates Phase 1 Subdivision Block
132;
We, AECOM; notify the Municipality that the above mentioned works were inspected on April 20, 2012 and to
the best of our knowledge and judgement, are complete in accordance with the Subdivision Agreement
except for the deficiencies below:
0 Items listed in AECOM Construction Status Report dated April 30, 2012,
Y Items listed in Valdor- Engineering Inc. letter dated April 11., 2012.
We hereby accept these works for use and operation by the Municipality subject to the rectification of the
above noted deficiencies and to the rectification of any further deficiencies that may become apparent during
the maintenance period and to the maintenance that is require by the Subdivision Agreement and its
Amendment
The date of Substantial Completion and Acceptance (Municipal Underground S /9rvices) is established by the
Certificate as of May 3, 2012.
Dater -, Z Signature