2010-177 Certificate of Substantial Completion - Moss DevTHE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
BY-LAW NO. 2010-177
Being a By-Law to Authorize the Issuance of the Certificate of
Substantial Completion and Acceptance (Municipal Underground Services)
for Moss Developments Ltd. (Country Lane Estates), Plan 51 M-946
WHEREAS Section 51, Subsection (26) of the Planning Act, R.S.O. 1990, Chapter
P. 13, as amended, provides that municipalities may enter into agreements imposed as
a condition to the approval of a plan of subdivision and such agreements may be
registered against the land to which the subdivision plan applies;
AND WHEREAS Council for the Corporation of the Township of Oro-Medonte entered
into a Subdivision Agreement with Moss Developments Ltd. (Country Lane Estates
Subdivision) in November 2009 for twenty (20) residential lots on Caldwell Drive.
AND WHEREAS the requirements of this Subdivision Agreement with respect to the
underground works have now been met;
NOW THEREFORE the Corporation of the Township of Oro-Medonte hereby enacts as
follows:
1. That the Certificate of Substantial Completion and Acceptance (Municipal
Underground Services) for Country Lane Estates Subdivision (Moss
Developments Ltd.), Plan 51 M-946 may now be issued by the Township
Engineers (AECOM) in compliance with the Subdivision Agreement between the
Corporation of the Township of Oro-Medonte and Moss Developments Ltd.
2. That the attached Schedule "A", Certificate of Substantial Completion and
Acceptance (Municipal Underground Services) shall form part of this By-Law.
3. That this By-law shall come into force and take effect on the final date of passing
thereof.
BY-LAW READ A FIRST, SECOND AND THIRD TIME, AND PASSED THIS 10TH DAY
OF NOVEMBER, 2010.
THE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
r, H.S. Hugbes
J. Dous Irwin
SCHEDULE "A"
ASCOM AECOM
10 Checkley Street 705 7219222 tel
Barrie, ON, Canada L4N 1W7 705 734 0764 (ax
VmMaecom.com
TOWNSHIP ENGINEERS
CERTIFICATE OF
SUBSTANTIAL COMPLETION AND ACCEPTANCE
(MUNICIPAL UNDERGROUND SERVICES)
MUNICIPALITY
Township of Oro-Medonte
PROJECT
Country Lane Estates Subdivision
Plan 51 M - 946
DEVELOPER
Moss Developments Ltd.
FILE NO.
1.2-89967-51 (43-OM-91050)
Description of the Works:
• SWM Facility in Blocks 22 & 26, including Storm Sewer, in the Country Lane Estates Subdivision;
• Fire Water Reservoir in Block 25 in the Country Lane Estates Subdivision;
We, AECOM, notify the Municipality that the above mentioned works were inspected on October 12, 2010,
and, to the best of our knowledge and judgement, are complete in accordance with the Subdivision
Agreement except for the deficiencies below:
e Items listed in AECOM Construction Status Report dated October 13, 2010.
We hereby accept these works for use and operation by the Municipality subject to the rectification of the
above noted deficiencies and to the rectification of any further deficiencies that may become apparent during
the maintenance period and to the maintenance that is required by the Subdivision Agreement and its
Amendment.
The date of Substantial Completion and Acceptance (Municipal Underground Services) is established by the
Certificate as of October 13, 2010.