2009-146 issuance of the Certificate of Maintenance and Final Acceptable (Aboveground and Underground Works) for Huronia HomesTHE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
BY-LAW NO. 2009-146
Being a By-Law to Authorize the Issuance of the Certificate of
Maintenance and Final Acceptable (Aboveground and Underground Works)
for Huronia Homes -Phase 2, Registered Plan 51 M-807
WHEREAS Section 51, Subsection (26) of the Planning Act, R.S.O. 1990, Chapter
P. 13, as amended, provides that municipalities may enter into agreements imposed as
a condition to the approval of a plan of subdivision and such agreements may be
registered against the land to which the subdivision plan applies;
AND WHEREAS Council for the Corporation of the Township of Oro-Medonte entered
into a Subdivision Agreement with Huronia Homes Ltd. in January 2005 to construct a
residential development consisting of twenty (20) lots on Hemlock Crescent.
AND WHEREAS the requirements of this Subdivision Agreement with respect to the
aboveground and underground works have now been met;
NOW THEREFORE the Corporation of the Township of Oro-Medonte hereby enacts as
follows:
That the Certificates of Maintenance and Final Acceptance (Aboveground and
Underground Works) for Huronia Homes Ltd., Registered Plan M-807 may now
be issued by the Township Engineers (Aecom) in compliance with the
Subdivision Agreement between the Corporation of the Township of Oro-
Medonte and Huronia Homes Ltd., Huronia Homes - Phase 2.
2. That the attached Schedule "A", Certificate of Maintenance and Final
Acceptance (Aboveground Works) shall form part of this By-Law.
3. That the attached Schedule "B", Certificate of Maintenance and Final
Acceptance (Underground Works) shall form part of this By-Law.
4. That this By-law shall come into force and take effect on the final date of passing
thereof.
BY-LAW READ A FIRST AND SECOND TIME THIS 28TH DAY OF OCTOBER, 2009.
BY-LAW READ A THIRD TIME AND FINALLY PASSED THIS 28T" DAY OF
OCTOBER, 2009.
THE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
, H.S. Vlughes
glas Irwin
Schedule "A" to By-law No. 2009-146
SCHEDULE "A"
I AECOM:
ACCOM
10 Checkley Straet, Barrie; ON, Canada t,4N 1 W1
T 705.72t9222 F705.734.0764 www.aecom.rom
TOWNSHIP ENGINEERS.
CERTIFICATE OF
MAINTENANCE AND FINAL ACCEPTANCE;
(ABOVEGROUND WORKS)
MUNICIPALITY
Township of Oro-Medonte
PROJECT
Huronia Homes Subdivision - Phase 2
Plan 51 M - 807
DEVELOPER
Huronia Homes Ltd.
FILE NO.
12-8911-51 IMMA 43T-9101'61
Description of the Works:
Roadways in the Huronia:H.omes Subdivision - Phase 2 consisting of,
Hemlock Crescent-from Bidwell -Road :to Bidwell Road, a_distanceof735 metres (4,411 feet).:
We, AECOM, notify the Municipality that the above mentioned works were inspected on October 8, 2009,
and to the best of our knowledge and judgement are complete in accordance with the Subdivision
Agreement, except for the deficiencies below:
NIL
We, AECOM, notify the Municipality that to the best of our knowledge and judgment:
1. The Developer named herein has completed the required maintenance work, has rectified known
deficiencies and has fulfilled the other terms of the Subdivision Agreement.
2. The period of maintenance; of this Subdivision Agreement exp' on the issuance of this Certificate.
RateSignature: dal
A1evW.W4M¢v.Aft-x:
Schedule t1B" to By-law No. 2009-146
SCHEDULE "B"
I AECQM
AECOM
10 Cheekfey Street, Banda, ON, Canada L4N 1W1
T705.721,9222 F ?05.734.0764 www aecom.com
TOWNSHIP ENGINEERS
CERTIFICATE OF MAINTENANCE AND FINAL ACCEPTANCE
(UNDERGROUND WORKS)
MUNICIPALITY Township of Oro-Medonte
PROJECT Huronia Homes Subdivision - Phase ,2
Plan 51 M - 807
DEVELOPER Huronia Homes Ltd.
FILE NO. 12-8911-51 (MMA 43T-91076)
Description of the Works:
• Storm sewer system and SWM Facility for Huronla Homes Subdivision Phase 2 on, Hemlock
Crescent.
We, AECOM, notify the Municipality that the above mentioned works were inspected on October 8, 2009,
and to the best of our knowledge and judgement are complete in accordance with the Subdivision
Agreement, excepfforthe deficiencies below:
• NIL
We, AECOM, notify the Municipality that to the;bestof our knowledge and judgment:
1. The Developer named herein has completed the required maintenance work, has rectified known
deficiencies and has fulfilled the other terms of the Subdivision Agreement.
2.. The period of maintenance of this Subdivision Agreement as on the issuanc of this Certificate.
pate!, Signature: `Ply'
' UM, M-q W;fd &F. A. P11, 2.