2008-009 To Authorize the Issuance of Certificate of Substantial Completion and Acceptance (Aboveground Works) for Arbourwood Estates Subdivision(Phase II), Pl 51M-696THE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
BY-LAW NO. 200$-009
Being a By-Law to Authorize the Issuance of Certificate of
Substantial Completion and Acceptance (Aboveground Works}
for Arbourwood Estates Subdivision (Phase II}, Plan 5'[ M-696
WHEREAS Section 224 of the Municipal Act, 2001, S.Q. 2401, c.25, as amended,
states that it is the role of Council to ensure that administrative policies, practices and
procedures are in place to implement the decisions of Council;
AND WHEREAS Section 51, Subsection (26) of the Planning Act, R.S.Q. 1990,
Chapter P.13, as amended, provides that municipalities may enter rota agreements
imposed as a condition to the approval of a plan of subdivision and such agreements
may be registered against the land to which the subdivision plan applies;
AND WHEREAS Council for the Corporation of the Township of Qro-Medonte entered
into a Subdivision Agreement with Arbourwood Estates Ltd. in October, 2002 to
construct Arbourwood Development, Phase II consisting of seventy-eight (78) lots in
the village of Shanty Bay.
AND WHEREAS the requirements of this Subdivision Agreement with respect to the
aboveground works have now been met;
NOW THEREFORE the Corporation of the Township of Qra-Medonte hereby enacts as
follows:
That the Certificate of Substantial Completion and Acceptance (Aboveground
Works) far Arbaurwood Estates Ltd., Phase II may now be issued by the
Township Engineers (Totten Sims Hubicki Associates} in compliance with the
Subdivision Agreement between the Corporation of the Township of Qro-
Medonte and Arbourwaad Estates Ltd.
2. That the attached Schedule "A", Certificate of Substantial Completion and
Acceptance (Aboveground Works} shall farm part of this By-Law.
3. That this By-law shall come into force and take effect on the final date of passing
thereof.
BY-LAW READ A FIRST AND SECOND TIME THIS 23RD DAY OF JANUARY, 2008.
BY-LAW READ A THIRD TIME AND FINALLY PASSED THIS 23R° DAY OF
JANUARY, 2008.
THE CORPQF~ATION OF THE TOWNSHIP OF ORO-MEDONTE
i ~ ~°"~~ ,
Mayor, H.S. Hughes
m ~ __
CI k, J. Daugfas Irwin
~~
• engineers
architects
planners
Schedule "A"
to By-Law No. 2008-009
TOWNSHIP ENGINEERS
CERTIFICATE OF
MUNICIPALITY
PROJECT
DEVELOPER
FILE NO.
Descriation of the Works:
SUBSTANTIAL COMPLETION AND ACCEPTANCE
ABOVEGROUND WORKS)
Township of Oro-Medonbe
Arbourwood Estates Subdivision Phase 2
Plan 51 M-696
Arbourwood Estates Ltd. Phase II
12-08921-b0 (MMA 43T- 92024)
Roadways in the Arbourwood Estates Subdivision Phase 2 cor~isting of:
• Red Oak Crescent westerly from the north end of Walnut Drive, and then southerty and
easterly to the south end of Walnut Drive; a distance of 1,420 metres (4,659 feet)
• Basswood Circle from Red Oak Crescent to Red Oak Crescent; a distance of 820 metres
(2,690 feet)
We, Totten Sims Hubidci, notify the Municipality that the above mentioned works were inspected
on December 11, 2007 and to the best of our knowledge and judgement, are complete in
accordance with the Subdivision Agreement except for the deficiencies below:
• Curb repair at Lot 90.
We hereby accept these works for use and operation by the Muniapality subject to the
rectification of the above noted deficiencies and to the rectification of any further deficiencies that
may become apparent during the maintenance period and to the maintenance that is require by
the Subdivision Agreement and its Amendment.
The date of Substantial Comp~tion and Acceptan vegrou/~orks) is established by the
Certificate as of geecember 11, 2007.
Dater `-~~'°~ Signature:
K:\8921-501Aboveground S.C. 8 Adoc