2006-018 To Authorize the Issuance of the Certificate of Substantial Completion and Acceptance (Underground Works) for Arbourwood Estates Limited
THE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
BY-LAW NO. 2006-018
Being a By-Law to Authorize the Issuance of the
Certificate of Substantial Completion and Acceptance (Underground Works) for
Arbourwood Estates Limited (Phase III), Registered Plan 51 M-767
WHEREAS Section 51, Subsection (26) of the Planning Act, R.S.O. 1990, Chapter P.13,
as amended, provides that municipalities may enter into agreements imposed as a
condition to the approval of a plan of subdivision and such agreements may be
registered against the land to which the subdivision plan applies;
AND WHEREAS Council for the Corporation of the Township of Oro-Medonte entered
into a Subdivision Agreement with Arbourwood Estates Limited (Phase III) in January,
2004.
AND WHEREAS the requirements of this Subdivision Agreement with respect to the
aboveground works have now been met;
NOW THEREFORE the Corporation of the Township of Oro-Medonte hereby enacts as
follows:
1 . That the Certificate of Substantial Completion and Acceptance (Underground
Works) for Arbourwood Estates Limited (Phase III), Registered Plan 51 M-767
may now be issued by the Township Engineers (Totten Sims Hubicki Associates)
in compliance with the Subdivision Agreement between the Corporation of the
Township of Oro-Medonte and Arbourwood Estates Limited (Phase III).
2. That the attached Schedule "A", Certificate of Substantial Completion and
Acceptance (Underground Works) shall form part of this By-Law.
3. That this By-law shall come into force and take effect on the final date of passing
thereof.
BY-LAW READ A FIRST AND SECOND TIME THIS 15TH DAY OF FEBRUARY, 2006.
BY-LAW READ A THIRD TIME AND FINALLY PASSED THIS 15TH DAY OF
FEBRUARY, 2006.
THE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
1 ~.~ tA",-/;-
I M or, J. Neil Craig
I
I
~~
archltec't8
planners
Sc.hedule "A" to By-Law No. 2006-01~
RG ROBINSON
~~(B..-.mlLw
._~
TOWNSBlP ENGINEERS
CERTIFICATE OF
SUBSTANTIAL COMPLETION AND ACCEPTANCE
(UNDERGROUND WORKS)
MUNICIPALITY
Township of Oro-Medonte
PROJECf
Arbourwood Estates Subdivision Phase 3
Plan 51M-767
DEVELOPER
Arbourwood Estates Limited (Ph. 3)
FILE NO.
12-8921-53 (OM-T-94004)
Descriution ofthe Works:
. Watennain distribution system and drainage outlets in Phase 3 in the Arbourwood Estates
Subdivision on Diane Court and Jenna Court.
We, R.G. Robinson and Associates (Barrie) Ltd.rrotten Sims Hubicki, notifY the Municipality that the
above mentioned works were inspected 00 Deeember 9, 2005 and to the best of our knowledge and
judgement, are complete in accordance with the Subdivision Agreement except for the deficiencies below;
. Nil
We hereby accept these works for use and operation by the Municipality subject to the rectification of the
above noted deficiencies and to the rectification of any further deficiencies that may become apparent
during the maintenance period and to the maintenance that is require by the Subdivision Agreement and its
Amendment.
The date of Substantial Completion and Acceptance (Under
as of December 9, 2005.
""" ,"'~U100t Si,,_
K'18921-53\Sub eomPI\U~erg;o~ s e & APh 3 doc
stablished by the Certificate