2004-139 To Authorize the Issuance of a Certificate of Maintenance and Final Acceptance (Underground Works) for Sugarbush Development, Phase III, Stage IV, Sections A and B
~
.
t
THE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
BY-LAW NO. 2004-139
Being a By-Law to Authorize the Issuance of a Certificate of Maintenance and
Final Acceptance (Underground Works) for Sugarbush Development,
Phase III, Stage IV, Sections A and B
WHEREAS Section 51, Subsection (26) of the Planning Act, R.5.0. 1990, Chapter P.13,
as amended, provides that municipalities may enter into agreements imposed as a
condition to the approval of a plan of subdivision and such agreements may be
registered against the land to which the subdivision plan applies;
AND WHEREAS Council for the Corporation of the Township of Oro-Medonte entered
into a Subdivision Agreement with Monica Interior Design Ltd. and Modco Investments
Ltd. in June, 2002;
AND WHEREAS the requirements of this Subdivision Agreement with respect to the
underground works have now been met;
NOW THEREFORE the Corporation of the Township of Oro-Medonte hereby enacts as
follows:
1. That the Certificate of Maintenance and Final Acceptance (Underground Works)
for Sugarbush Development, Phase III, Stage IV, Sections A and B may now be
issued by the Township Engineer (R.G. Robinson & Associates) in compliance
with the Subdivision Agreement between the Corporation of the Township of
Oro-Medonte and Monica Interior Design Ltd. and Modco Investments Ltd. in
June, 2002;
2. That the attached Schedule "A", Certificate of Maintenance and Final Acceptance
(Undergound Works), shall form part of this By-Law.
3. That this By-law shall come into force and take effect on the final date of passing
thereof.
By-law read a first and second time this 15th day of December, 2004.
By-law read a third time and finally passed this 15th day of December, 2004.
THE CORPORATION OF THE TOWNSHIP OF ORO-MEDONTE
.....
Ma~,j.~//~(j
~,
}
..
;.
Schedule "A" to By-Law No. 2004-139
.
R.G. ROBINSON AND ASSOCIATES (BARRIE) LTD.
TOWNSHIP ENGINEERS
CERTIFICATE OF
MAINTENANCE AND FINAL ACCEPTANCE
(UNDERGROUND WORKS)
MUNICIPALITY
Township of Oro-Medonte
PROJECT
Sue:arbush Phase III. Stae:e IV - Sections "A" and "B"
DEVELOPER
Monica Interior Design Ltd. and
Modco Investments Ltd.
FILE NO.
12-8847-50
Description ofthe Works:
. Watermain distribution system and storm drainage works in Sections "A" and "B" of the Sugarbush
Phase III, Stage IV Subdivision consisting of:
Section "A" - 6th Line ofOro-Medonte between Huron Woods Drive and Ash Court.
Section "B" - Ironwood Trail from Huron Woods Drive to Station 0 + 250.
We, R.G. Robinson and Associates (Barrie) Ltd., notify the Municipality that the above mentioned works
were inspected on November 15, 2004, and to the best of our knowledge and judgement, are complete in
accordance with the Subdivision Agreement except for the deficiencies below:
We, R.G. Robinson and Associates (Barrie) Ltd. , notify the Municipality that to the best of our knowledge
and judgement:
1. The Developer named herein has completed the required maintenance work, has rectified known
deficiencies and has fulfilled the other terms of the Subdivision Agreement.
2. The period of maintenance of this Subdivision Agreement expires on the issuance ofthis Certificate.
File # 12-8847-50